US 221 Widening in the Isothermal Region–Updated November 2017

us221-rutherford2017

In 2016-2025 STIP, R-2233BB is funded with ROW (property acquisition) starting in FY 2018 and construction slated for FY 2020. The BA section was funded in the 2018-2027 draft STIP. Currently, property acquisition is scheduled for FY 2022 and construction in FY 2025.

 

R-0204E is in the 2018-2027 STIP with a ROW data of FY2021 and construction in FY2023. None of the other sections are currently funded. All of the unfunded sections will be in SPOT 5 which is slated to begin Summer 2017.